Get enough slope on the slab. From front to back at 12 feet, I would do 10" fall. I have 12" on 16 foot. Works out great and mine is smooth trialed, not broomed and it hoses off real nice. I also took an 10 Dia. under ground water
line pipe and cut them in half long ways and fastened it to the concrete for a gutter. Also fastened a treated 2 x 6 to both sides of the slab so all water is kept within the gutter area when cleaned. I'll post a pic for ya on Friday. I have 3 10 x 10 set up on mine. As far as draing it all into a field tike, not a good Idea unless you screen the front on the tile. I have a 10" running from gutter to a drainage ditch and it can get clogged up with straw and shaving at times. Have to clean it out and it's only 7 foot long to the ditch. Good luck with it!! Face it East!!